Use this function to generate the plan drawing of all the trenches of the active Water and Sewer project.

  • It has to be considered that the drawing generated, reflects the model at the time of generating the drawing.
  • If the project is modified, the plan has to be regenerated (run the function Plan again) to update.
  • The scale governs the drawing.
  • Drawing setup of different pipes, connections, materials, etc., is defined through the function Start Configuration and the sub-functions Ditch, Pipes, Pipe Materials, Connectors and Connector Materials.
  • Properties such as layers, colour, linetypes, etc., are set for the individual pipe types with the sub-functions “Pipes” and “Settings > Confiuration” of Start Configuration.

Run the function from the following locations:

MOUS_ICO Menu: Water and Sewer > Drawing Plan
MOUS_ICO Toolbar: Drawing: Plan

* The function has no related dialog box and generates the drawing based on the current project.

  • When the drawing is generated, text related to connectors will frequently be placed on top of other text.

Use the central grip of the circle and the text (text entity is group of circle, text and leader line) to relocate such overlapping texts. The leader line will be adjusted automatically to the new location of the text.